Midas Gold Project

Project Highlights:

  • Tailings Storage Facility Design
  • Geotechnical Engineering
  • Civil Engineering
  • Site-wide Hydrology
  • Site-wide Water Balance
  • Diversion Design
  • Pre-Feasibility Study

Midas Gold’s project is located in the remote central Idaho Rockies near the town of Yellow Pine.  It is a brownfields gold-antimony project featuring three open pits and an anticipated 22,000 tpd plant throughput, along with challenging terrain and environmental constraints. Tierra Group completed the preliminary feasibility design for the proposed tailings storage facility, water diversions, and site-wide water management, including relevant content for the NI-43-101-compliant prefeasibility technical report. Tierra Group also completed TSF and water diversion designs and completed reclamation cost estimating for a NI 43-101 compliant feasibility study published in January 2020. Tierra Group also completed engineering analyses and design for federal and state permitting.

The TSF will be lined with a composite geosynthetic liner system. A rockfill buttress will be built in multiple stages during project development. Diversions will redirect a perennial mountain stream around the TSF. Tierra Group continues supporting Midas by completing detailed design and permitting support.

Project Highlights:

  • Tailings Storage Facility Design
  • Geotechnical Engineering
  • Civil Engineering
  • Site-wide Hydrology
  • Site-wide Water Balance
  • Diversion Design
  • Pre-Feasibility Study

Similar projects

Anaconda Mine

Tailings Storage Trade-Off Study Tierra Group completed trade-off studies evaluating potential TSF sites to store 25 million tonnes of tailings. Trade-off studies included dam layouts, cost estimating, and recommendations for future work. Trade-off study challenges were minimizing costs while still…

VIEW PROJECT

Tailings Assurance Audit | Canada

Tierra Group completed a Tailings Assurance Audit (TAA) for a closed Tailings Storage Facility (TSF). The TAA was completed to ensure the TSF and site operations complied with the Company's Tailings Management Standard, which closely mirrors Global Industry Standard on…

VIEW PROJECT

La Trinidad

Tierra Group began work at La Trinidad providing heap leach pad construction recommendations and a water balance. Tierra Group continued support with a heap leach pad expansion design, slope stability analyses, hydrologic analyses, diversion design, liner design, and leach solution…

VIEW PROJECT

Brushy Creek

Tierra Group provided a raise design for Doe Run's Brushy Creek tailings embankment, a facility first commissioned in 1973. Cone penetration testing, liquefaction analysis, seepage modeling, and slope stability modeling were performed for the embankment. Hydrology, spillway design, and impoundment layout…

VIEW PROJECT

Oracle Ridge Copper

Tierra Group represented Oracle Ridge Mining as the Qualified Person for portions of the feasibility-level design including the Dry Stack Tailings Storage Facility (TSF) Design, Site-Wide Stormwater Management, Water Supply Pipelines, Haul Road and Access Road Design Improvements, and the…

VIEW PROJECT

Mission Mine

Tierra Group is implementing a corporate Tailings Stewardship Strategy (TSS) at all of ASARCO Grupo Mexico’s mines in Arizona, USA (Hayden, Mission and Ray mines). Tierra Group conducted a site visit to each site to perform dam safety inspections, interview…

VIEW PROJECT

Myra Falls

Tierra Group provides Tailings Stewardship Services for Nyrstar's Myra Falls Mine Tailings Storage Facility. Tierra Group performed a 5-year Dam Safety Review consistent with the Canadian Dam Association protocols, site training and in depth inspections of management practices and facilities…

VIEW PROJECT

El Aguila

Dry Stack Tailings Options Analysis Tierra Group performed an independent TSF expansion engineering design peer review. The review resulted in cost savings ($650,000) without compromising the facility's design integrity over the original design. Tierra Group also provided full-time CQA. Tierra…

VIEW PROJECT

Buriticá Tailings Stewardship & Cyanide Speciation

Tierra Group provided Tailings Stewardship Services for Continental Gold’s Buriticá Project in Antioquia, Columbia which included permitting support, Third-Party Review and construction and operations support. Tierra Group oversaw the development of a 2D hydrodynamic model to support the design of…

VIEW PROJECT

NioCorp’s Elk Creek | Tailings Storage Facility (TSF) Feasibility Study

Tierra Group advanced the TSF design to a Feasibility Level according to the Canadian National Instrument NI 43-101 and the U.S. Security and Exchange Commission’s Subpart SK-1300 regulation. Tierra Group’s scope of work included a geotechnical investigation, engineering analysis, and TSF…

VIEW PROJECT

Palmarejo Mine

Tierra Group performed an initial site visit to Coeur Mining’s Palmarejo Mine to conduct dam safety inspections of the tailings storage facility, environmental control dam, water diversion dam, and water diversion channel. Prior to the site visit, Tierra Group reviewed…

VIEW PROJECT

Dam Assessment

Tierra Group performed a site visit and visual inspection of a dam to assess its overall condition and provide the Owner recommendations for continued maintenance, monitoring, and improvements. The assessment was a follow-up to previous work completed by Tierra Group…

VIEW PROJECT