Sweetwater Mine

Project Highlights:

  • Permitting
  • Tailings Operations Planning
  • CQA
  • Liquefaction
  • Seismic Stability
  • Slope Stability Analysis
  • Engineer of Record
  • Conventional Tailings

Sweetwater Mine Permitting

Tierra Group’s Team began work at the Sweetwater mine in 1993 assisting permitting and developing tailings impoundment management strategies for the mine. We successfully designed and installed an innovative internal seal for repair of the mine’s damaged decant discharge conduit. Tierra Group began working at Sweetwater again in 2015 designing a 5 foot TSF dam and spillway raise. Unique design challenges were overcome with a comprehensive field investigation including CPT and hollow stem auger drilling. Liquefaction analyses were performed and incorporated into the upstream raise design. A challenging hydrology model was completed and a raise to the existing spillway was designed. The raise design was approved by MDNR Dam and Reservoir Safety council in March 2016. Construction was completed in early 2017 with support provided with Tierra Group overseeing construction activities and evaluating proposed design changes. An As-Built report was completed in April 2017 conforming to MDNR requirements. Tierra Group provided additional support at Sweetwater by designing a 23 foot dam raise providing more than 15 years additional tailings capacity. A new spillway and saddle dam was included in the design. The dam raise design was approved by MDNR in July 2018. Tierra Group supported dam raise construction in 2021 completing design optimizations that reduced construction costs, supporting construction, and completing an as-built report.

Project Highlights:

  • Permitting
  • Tailings Operations Planning
  • CQA
  • Liquefaction
  • Seismic Stability
  • Slope Stability Analysis
  • Engineer of Record
  • Conventional Tailings

Similar projects

Anaconda Mine

Tailings Storage Trade-Off Study Tierra Group completed trade-off studies evaluating potential TSF sites to store 25 million tonnes of tailings. Trade-off studies included dam layouts, cost estimating, and recommendations for future work. Trade-off study challenges were minimizing costs while still…

VIEW PROJECT

Myra Falls

Tierra Group provides Tailings Stewardship Services for Nyrstar's Myra Falls Mine Tailings Storage Facility. Tierra Group performed a 5-year Dam Safety Review consistent with the Canadian Dam Association protocols, site training and in depth inspections of management practices and facilities…

VIEW PROJECT

Midas Mine

The Midas Mine is located in northern Nevada, and is owned and operated by Hecla Mining Company.  The mine is an underground mine with an operating mill. The mine’s existing tailings facilities are nearing their end of operating life and…

VIEW PROJECT

Pierina Mine

Barrick Gold Corporation’s Pierina Mine in Ancash Department, Perú began operations in 1998. A progressive reclamation and closure plan began in 2013.  In 2015-16 Tierra Group developed detailed engineering designs for channels, sediment traps, two 45,000 m3 sediment ponds, water…

VIEW PROJECT

San Albino Dry Stack Tailings Storage Facility Design

Tierra Group supported construction of the San Albino Mine in Nueva Segovia, Nicaragua. Tierra Group designed a dry stack drum filtered-tailings storage facility. A siting study optimized the dry stack location and minimized CAPEX and OPEX. Tierra Group developed a site-wide water…

VIEW PROJECT

Don Mario Gold Mine

Don Mario Mine is an open pit gold/copper mine located in the Chiquitos Province, Santa Cruz, Bolivia that has been operating since 2002 and currently produces 2700 tpd mill throughput. Conventional tailings are transported and deposited in a high-density polyethylene lined geomembrane valley…

VIEW PROJECT

Cerro Negro

Tierra Group was selected to assist Goldcorp with global Tailings Stewardship Strategy (TSS) implementation at all of Goldcorp’s active tailings sites in Latin America (Mexico, Argentina, and Guatemala). Tierra Group worked in conjunction with Goldcorp and another global engineering consulting…

VIEW PROJECT

El Aguila

Tierra Group performed a 3rd party engineering design peer review of a tailings storage facility expansion design. The review resulted in the owner realizing $650,000 in cost savings without compromising the facility's design integrity over the original design. Tierra Group also…

VIEW PROJECT

Oracle Ridge Copper

Tierra Group represented Oracle Ridge Mining as the Qualified Person for portions of the feasibility-level design including the Dry Stack Tailings Storage Facility (TSF) Design, Site-Wide Stormwater Management, Water Supply Pipelines, Haul Road and Access Road Design Improvements, and the…

VIEW PROJECT

Topia Mine

Topia Mine Phases 1-3Tierra Group supervised the first 3 phases of Geologic Mapping and Instrumentation Installation and developed a Mechanically Stabilized Earth Wall Design at Great Panther Silver’s Topia Mine in Durango, Mexico.

VIEW PROJECT

Orotex Mine Project

Tierra Group provided tailings engineering design and consulting services for the redevelopment of the Orotex underground mine in Alajuela, Costa Rica. Tierra Group's areas of responsibility included tailings and water management in this environmentally sensitive, high rainfall, tropical, mountainous region.

VIEW PROJECT

Rosario Mine

Tierra Group performed a Dam Safety Review (DSR) including geotechnical investigations and seepage and slope stability analyses for a 20-m high TSF at this 300‑tpd underground polymetallic mine. The audit was prepared following the Mt. Polley tailings dam failure in…

VIEW PROJECT