Sweetwater Mine

Project Highlights:

  • Permitting
  • Tailings Operations Planning
  • CQA
  • Liquefaction
  • Seismic Stability
  • Slope Stability Analysis
  • Engineer of Record
  • Conventional Tailings

Sweetwater Mine Permitting

Tierra Group’s Team began work at the Sweetwater mine in 1993 assisting permitting and developing tailings impoundment management strategies for the mine. We successfully designed and installed an innovative internal seal for repair of the mine’s damaged decant discharge conduit. Tierra Group began working at Sweetwater again in 2015 designing a 5 foot TSF dam and spillway raise. Unique design challenges were overcome with a comprehensive field investigation including CPT and hollow stem auger drilling. Liquefaction analyses were performed and incorporated into the upstream raise design. A challenging hydrology model was completed and a raise to the existing spillway was designed. The raise design was approved by MDNR Dam and Reservoir Safety council in March 2016. Construction was completed in early 2017 with support provided with Tierra Group overseeing construction activities and evaluating proposed design changes. An As-Built report was completed in April 2017 conforming to MDNR requirements. Tierra Group provided additional support at Sweetwater by designing a 23 foot dam raise providing more than 15 years additional tailings capacity. A new spillway and saddle dam was included in the design. The dam raise design was approved by MDNR in July 2018. Tierra Group supported dam raise construction in 2021 completing design optimizations that reduced construction costs, supporting construction, and completing an as-built report.

Project Highlights:

  • Permitting
  • Tailings Operations Planning
  • CQA
  • Liquefaction
  • Seismic Stability
  • Slope Stability Analysis
  • Engineer of Record
  • Conventional Tailings

Similar projects

Los Gatos Project

TSF Design and CQA Tierra Group provided detailed Stage 1 and 2 Tailings Storage Facility design, conducted a process plant geotechnical foundation investigation, and provided Construction Quality Assurance for Sunshine Silver Mining's Los Gatos Project in Chihuahua, Mexico. Tierra Group then…

VIEW PROJECT

Campo Morado Mine

Tierra Group performed a Dam Safety Review (DSR) for Nyrstar’s tailings storage facility (TSF) located in Campo Morado (Guerrero, Mexico).  Tierra Group served as the Tailings Reviewer to ensure conformity with local regulations, the Nyrstar Tailings Storage Facility (TSF) Standard,…

VIEW PROJECT

Los Filos Mine

Tierra Group was selected to assist Goldcorp with global Tailings Stewardship Strategy (TSS) implementation at all of Goldcorp’s active tailings sites in Latin America (Mexico, Argentina, and Guatemala). Tierra Group worked in conjunction with Goldcorp and another global engineering consulting…

VIEW PROJECT

Pitarrilla Mine

Tierra Group participated as a member of a multi-disciplinary project team to develop a Definitive Feasibility study for a 16,000 tpd silver mine in Durango, Mexico. Tierra Group's responsibilities included designing a 112 Mt tailings storage facility, developing a site-wide…

VIEW PROJECT

Marlin Mine

Tierra Group provides Tailings Stewardship Services for the Marlin Mine Tailings Storage Facility. Tierra Group performed a 5-year Dam Safety Review consistent with the Canadian Dam Association protocols, a Facilitated Risk Assessment, site training and in depth inspections of management…

VIEW PROJECT

Dam Low Level Outlet Replacement

Tierra Group completed a geotechnical investigation, which included overseeing hollow stem auger (HSA) drilling and laboratory testing, that characterized the existing earthen dam. Tierra Group completed a low-level outlet structure design that was believed to have been compromised by internal…

VIEW PROJECT

Masbate Mine

Tierra Group performed a study of Masbate’s 12-Mt tailings storage facility. Services provided included a forensic study to determine the cause of seepage through an abutment and performed an independent safety audit of tailings management practices. A risk analysis was performed…

VIEW PROJECT

Douglas County Public Works

Tierra Group updated the County’s Standard Operating Procedures (SOPs) for Municipal Operations to maintain the County’s compliance with the requirements for stormwater discharges from the County’s municipal separate storm sewer system (MS4) under the Colorado Discharge Permit System (CDPS). Tierra…

VIEW PROJECT

La Negra Mine

Tierra Group performed a tailings storage facility safety (TSF) audit for the 90 m high upstream constructed tailings dam at La Negra Mine in Querétaro, Mexico. The project included a TSF dam inspection and Dam Safety Inspection Report (DSIR) containing operational…

VIEW PROJECT

Bolivar Mine

The Bolivar mine is a 3,000 tonne per day underground mining operation in Chihuahua, Mexico producing copper, zinc, silver, and gold. Space constraints in mountainous terrain require dewatering tailings to reduce required area for tailings storage. Tierra Group is assisting…

VIEW PROJECT

Newcrest Red Chris Tailings Stewardship

Tierra Group provided Tailings Stewardship Services for TSFs and water dams at the Cadia, Terfer, and Red Chris properties. Responsibilities included data/report review; identifying and assisting the client with managing risks, liabilities, controls, and reporting; evaluating progress towards GISTM compliance;…

VIEW PROJECT

Newcrest Telfer Tailings Stewardship

Tierra Group provided Tailings Stewardship Services for TSFs and water dams at the Cadia, Terfer, and Red Chris properties. Responsibilities included data/report review; identifying and assisting the client with managing risks, liabilities, controls, and reporting; evaluating progress towards GISTM compliance;…

VIEW PROJECT