Sweetwater Mine

Project Highlights:

  • Permitting
  • Tailings Operations Planning
  • CQA
  • Liquefaction
  • Seismic Stability
  • Slope Stability Analysis
  • Engineer of Record
  • Conventional Tailings

Sweetwater Mine Permitting

Tierra Group’s Team began work at the Sweetwater mine in 1993 assisting permitting and developing tailings impoundment management strategies for the mine. We successfully designed and installed an innovative internal seal for repair of the mine’s damaged decant discharge conduit. Tierra Group began working at Sweetwater again in 2015 designing a 5 foot TSF dam and spillway raise. Unique design challenges were overcome with a comprehensive field investigation including CPT and hollow stem auger drilling. Liquefaction analyses were performed and incorporated into the upstream raise design. A challenging hydrology model was completed and a raise to the existing spillway was designed. The raise design was approved by MDNR Dam and Reservoir Safety council in March 2016. Construction was completed in early 2017 with support provided with Tierra Group overseeing construction activities and evaluating proposed design changes. An As-Built report was completed in April 2017 conforming to MDNR requirements. Tierra Group provided additional support at Sweetwater by designing a 23 foot dam raise providing more than 15 years additional tailings capacity. A new spillway and saddle dam was included in the design. The dam raise design was approved by MDNR in July 2018. Tierra Group supported dam raise construction in 2021 completing design optimizations that reduced construction costs, supporting construction, and completing an as-built report.

Project Highlights:

  • Permitting
  • Tailings Operations Planning
  • CQA
  • Liquefaction
  • Seismic Stability
  • Slope Stability Analysis
  • Engineer of Record
  • Conventional Tailings

Similar projects

Cerro Negro

Tierra Group was selected to assist Goldcorp with global Tailings Stewardship Strategy (TSS) implementation at all of Goldcorp’s active tailings sites in Latin America (Mexico, Argentina, and Guatemala). Tierra Group worked in conjunction with Goldcorp and another global engineering consulting…

VIEW PROJECT

NioCorp’s Elk Creek | Tailings Storage Facility (TSF) Feasibility Study

Tierra Group advanced the TSF design to a Feasibility Level according to the Canadian National Instrument NI 43-101 and the U.S. Security and Exchange Commission’s Subpart SK-1300 regulation. Tierra Group’s scope of work included a geotechnical investigation, engineering analysis, and TSF…

VIEW PROJECT

San Francisco Mine

Tierra Group conducted geo-electrical testing to locate leaks present in the geomembrane liners underlying a Solution Conveyance Canal, Sumps 1 and 2, and the Intermediate Pond at Timmins Gold Corp’s San Francisco Mine in Sonora, Mexico. Leak detection testing procedures…

VIEW PROJECT

New Jersey Mill TSF Scoping Study

Tierra Group completed the design for two 3-meter upstream raises to an existing paste tailings storage facility at New Jersey Mining Company’s New Jersey Mill site near Kellogg, Idaho. Work included performing a cone penetration testing (CPT) investigation of the…

VIEW PROJECT

Isabella Pearl

Tierra Group performed a technical peer review of the Isabella Pearl heap leach facility (HLF) owned by Gold Resource Corporation. Isabella Pearl mine is located at the west end of the Santa Fe mining district in the Walker Lane gold…

VIEW PROJECT

Oracle Ridge Copper

Tierra Group represented Oracle Ridge Mining as the Qualified Person for portions of the feasibility-level design including the Dry Stack Tailings Storage Facility (TSF) Design, Site-Wide Stormwater Management, Water Supply Pipelines, Haul Road and Access Road Design Improvements, and the…

VIEW PROJECT

Bolivar Mine

The Bolivar mine is a 3,000 tonne per day underground mining operation in Chihuahua, Mexico producing copper, zinc, silver, and gold. Space constraints in mountainous terrain require dewatering tailings to reduce required area for tailings storage. Tierra Group is assisting…

VIEW PROJECT

Andina Veladero Engineering Review

Tierra Group performed a forensic study to determine the cause for volumetrically non-compliant leakage volumes occurring in the heap leach facilities leak detection system. Tierra Group reviewed the facility design, engineering and construction quality assurance (CQA) information, construction as built…

VIEW PROJECT

Marlin Mine

Tierra Group provides Tailings Stewardship Services for the Marlin Mine Tailings Storage Facility. Tierra Group performed a 5-year Dam Safety Review consistent with the Canadian Dam Association protocols, a Facilitated Risk Assessment, site training and in depth inspections of management…

VIEW PROJECT

San Andrés Mine

Previous to Tierra Group, our Team performed a geotechnical forensics assessment, which determined that spent ore from an on-off leach pad operation had liquefied causing a debris flow, which threatened inundating a major river basin. A preventative detention buttress was…

VIEW PROJECT

Caeté Complex

Tierra Group developed a site-wide water management plan, and performed a liquefaction potential study following the Samarco tailings dam failure in Minas Gerais, Brazil. A tailings storage facility water balance was developed to optimize water usage and minimize risks at…

VIEW PROJECT

Bolanitos

Tierra Group provided Tailings Stewardship Services including a dam inspection, slope stability analysis review and operational improvements for Endeavour Silver’s Bolanitos tailings storage facility.

VIEW PROJECT