Mascota Mine

Project Highlights:

  • Heap Leach Design
  • Civil Design
  • Geotechnical Investigation
  • Water Balance
  • Buttress Design
  • Construction Quality Assurance

Creston Mascota Mine is located in Chihuahua, Mexico and is owned and operated by Agnico Eagle Mexico. Tierra Group designed the Phase 4 heap leach pad, buttress, which included geotechnical investigations, slope stability analyses and a water balance for Agnico Eagle’s Mascota Mine 5,000 tpd heap leach pad (combined with Pinos Altos ore) in Chihuahua, Mexico. In addition, Tierra Group provided Construction Quality Assurance (CQA) services for phase 3 and phase 4 pad construction.

Phase 5 Heap Leach Pad is an expansion of Phase 4 with a proposed capacity of 2 to 3 million tons (Mt) of crushed ore. The project includes development of construction drawings and technical specifications to be used for the construction of the facility. The design includes slope stability analyses, seepage analyses, water balance to verify the size of existing ponds, and stormwater management to design diversion channels.

Tierra Group will also provide Construction Quality Assurance (CQA) services for the construction of the heap expansion, including construction observation, clay placement and compaction, and liner installation.

Project Highlights:

  • Heap Leach Design
  • Civil Design
  • Geotechnical Investigation
  • Water Balance
  • Buttress Design
  • Construction Quality Assurance

Similar projects

American Gypsum

American Gypsum Pit Planning and Support Tierra Group began working at American Gypsum’s Eagle-Gypsum mine located in Gypsum, Colorado in 2014 evaluating haul road improvements. A trade-off study provided a tool for American Gypsum to evaluate safety improvements including alternative haul road…

VIEW PROJECT

Lagunas Norte Mine

The Lagunas Norte Mine, operated by Barrick Misquichilca S.A., is an open pit gold mine located in the Quiruvilca district, Santiago de Chuco province, La Libertad department, Perú. The main study objective was to evaluate the volume of effluent discharge…

VIEW PROJECT

Brushy Creek 2

Tierra Group was commissioned by Doe Run to design a new tailings storage facility at the Brushy Creek Mine. Tierra Group completed a geotechnical investigation including boring, classifying, and sampling soil and rock. Trade-off studies were performed to minimize construction…

VIEW PROJECT

Brushy Creek

Tierra Group provided a raise design for Doe Run's Brushy Creek tailings embankment, a facility first commissioned in 1973. Cone penetration testing, liquefaction analysis, seepage modeling, and slope stability modeling were performed for the embankment. Hydrology, spillway design, and impoundment layout…

VIEW PROJECT

Masbate Mine

Tierra Group performed a study of Masbate’s 12-Mt tailings storage facility. Services provided included a forensic study to determine the cause of seepage through an abutment and performed an independent safety audit of tailings management practices. A risk analysis was performed…

VIEW PROJECT

Rhyolite Ridge

Tierra Group is providing water management and geotechnical engineering services to support a Preliminary Feasibility Study at the Rhyolite Ridge Lithium Mine Project in Nevada.

VIEW PROJECT

Caeté Complex

Tierra Group developed a site-wide water management plan, and performed a liquefaction potential study following the Samarco tailings dam failure in Minas Gerais, Brazil. A tailings storage facility water balance was developed to optimize water usage and minimize risks at…

VIEW PROJECT

San Bartolome Mine | NI 43-101 Tailings Technical Review & Report

Tierra Group performed an Independent Tailings Technical Review to support the San Bartolomé Mine Prefeasibility Study (PFS) NI 43-101 Technical Report (TR). SRK Consulting Inc. (SRK) is the primary TR author. Tierra Group will provided a Qualified Person (QP) to oversee…

VIEW PROJECT

Yauricocha Mine

The Yauricocha Mine is a polymetallic (copper, lead, zinc) underground mine located in Yauyos Province, Lima, Peru. Tailings are deposited in the Yauricocha Tailings Storage Facility (TSF) located 3km from the process plant. Tierra Group was engaged in 2015 to…

VIEW PROJECT

Douglas County Public Works

Tierra Group updated the County’s Standard Operating Procedures (SOPs) for Municipal Operations to maintain the County’s compliance with the requirements for stormwater discharges from the County’s municipal separate storm sewer system (MS4) under the Colorado Discharge Permit System (CDPS). Tierra…

VIEW PROJECT

El Cubo

Tierra Group provided Tailings Stewardship Services including a dam inspection, slope stability analysis review and operational improvements for Endeavour Silver’s El Cubo tailings storage facility in Guanajuato, Mexico.

VIEW PROJECT

Aurora Mine

The Aurora Mine Mill Facility (previously Esmeralda Mill) is located in the historic Aurora mining district of the eastern Sierra Nevada Mountain Range in Nevada, USA. Aurora recently, with the support of Tierra Group completed a Minor Modification to the…

VIEW PROJECT