Tierra Group diseñó el TSF de pila seca de Bunker Hill. El diseño del TSF fue un desafío debido a la superficie terrestre limitada, el terreno empinado, el clima frío estacional y la gestión del agua superficial. El alcance del trabajo de Tierra Group incluyó la ubicación de las instalaciones, investigaciones geotécnicas, diseño civil, controles de aguas superficiales, diseño de contención y análisis geotécnicos.
Tierra Group completed a geotechnical investigation, which included overseeing hollow stem auger (HSA) drilling and laboratory testing, that characterized the existing earthen dam. Tierra Group completed a low-level outlet structure design that was believed to have been compromised by internal…
Dam Breach Analyses Tierra Group prepared a DBA to evaluate potential downstream impacts due to a hypothetical failure (breach) in three components of Empire State Mines (ESM) tailings storage facility (TSF): North Dam (ND), South Dam (SD), and West Perimeter…
Serving on Newmont Goldcorp’s Tailings Independent Review Board, Tierra Group provided an Independent Dam Safety Review for the Dona Lake Mine tailings storage facility in Pickle Lake, Ontario, Canada.
Tierra Group assisted with developing tailings disposal alternatives.
The Bolivar mine is a 3,000 tonne per day underground mining operation in Chihuahua, Mexico producing copper, zinc, silver, and gold. Space constraints in mountainous terrain require dewatering tailings to reduce required area for tailings storage. Tierra Group is assisting…
Tierra Group provided design review and technical direction at Hod Mine in the Artvin Province of Turkey. Work included detailed design of potentially acid generating and non-acid generating waste dump facilities, their appurtenant structures and stormwater management design for the…
Tierra Group provided a raise design for Doe Run's Brushy Creek tailings embankment, a facility first commissioned in 1973. Cone penetration testing, liquefaction analysis, seepage modeling, and slope stability modeling were performed for the embankment. Hydrology, spillway design, and impoundment layout…
Tierra Group performed an independent engineering design review of a Cemented Tailings Facility (CTF) and multiple processes and freshwater ponds. Tailings will be mixed with cement at the paste plant and deposited in the CTF along with underground mine development…
Tailings Management Assurance Review Tierra Group served as the Lead Auditor and conducted MARs for the TSFs at this confidential project. Tierra Group reviewed all available facility documentation, including OMS Manuals, EAPs, design reports, As-Built Reports, annual inspection reports, and other…
Tierra Group provided a Third-Party review of the Hermosa Project Tailings Storage Facility Design and Construction stages 1 & 2 in Patagonia, Arizona
Dry Stack Tailings Storage Facility Tierra Group designed a dry stack TSF to store excess tailings from the underground paste backfill. The dry stack TSF was challenging, given the limited land area, steep terrain, seasonal cold weather, and surface water…
Tierra Group was commissioned by Doe Run to design a new tailings storage facility at the Brushy Creek Mine. Tierra Group completed a geotechnical investigation including boring, classifying, and sampling soil and rock. Trade-off studies were performed to minimize construction…
Tierra Group completed a geotechnical investigation, which included overseeing hollow stem auger (HSA) drilling and laboratory testing, that characterized the existing earthen dam. Tierra Group completed a low-level outlet structure design that was believed to have been compromised by internal…
Dam Breach Analyses Tierra Group prepared a DBA to evaluate potential downstream impacts due to a hypothetical failure (breach) in three components of Empire State Mines (ESM) tailings storage facility (TSF): North Dam (ND), South Dam (SD), and West Perimeter…
Serving on Newmont Goldcorp’s Tailings Independent Review Board, Tierra Group provided an Independent Dam Safety Review for the Dona Lake Mine tailings storage facility in Pickle Lake, Ontario, Canada.
Tierra Group assisted with developing tailings disposal alternatives.
The Bolivar mine is a 3,000 tonne per day underground mining operation in Chihuahua, Mexico producing copper, zinc, silver, and gold. Space constraints in mountainous terrain require dewatering tailings to reduce required area for tailings storage. Tierra Group is assisting…
Tierra Group provided design review and technical direction at Hod Mine in the Artvin Province of Turkey. Work included detailed design of potentially acid generating and non-acid generating waste dump facilities, their appurtenant structures and stormwater management design for the…
Tierra Group provided a raise design for Doe Run's Brushy Creek tailings embankment, a facility first commissioned in 1973. Cone penetration testing, liquefaction analysis, seepage modeling, and slope stability modeling were performed for the embankment. Hydrology, spillway design, and impoundment layout…
Tierra Group performed an independent engineering design review of a Cemented Tailings Facility (CTF) and multiple processes and freshwater ponds. Tailings will be mixed with cement at the paste plant and deposited in the CTF along with underground mine development…
Tailings Management Assurance Review Tierra Group served as the Lead Auditor and conducted MARs for the TSFs at this confidential project. Tierra Group reviewed all available facility documentation, including OMS Manuals, EAPs, design reports, As-Built Reports, annual inspection reports, and other…
Tierra Group provided a Third-Party review of the Hermosa Project Tailings Storage Facility Design and Construction stages 1 & 2 in Patagonia, Arizona
Dry Stack Tailings Storage Facility Tierra Group designed a dry stack TSF to store excess tailings from the underground paste backfill. The dry stack TSF was challenging, given the limited land area, steep terrain, seasonal cold weather, and surface water…
Tierra Group was commissioned by Doe Run to design a new tailings storage facility at the Brushy Creek Mine. Tierra Group completed a geotechnical investigation including boring, classifying, and sampling soil and rock. Trade-off studies were performed to minimize construction…
Tierra Group completed a geotechnical investigation, which included overseeing hollow stem auger (HSA) drilling and laboratory testing, that characterized the existing earthen dam. Tierra Group completed a low-level outlet structure design that was believed to have been compromised by internal…